Approx. value of the contract: 9.6 million PKR | |
Country
Pakistan |
Location within Country (Districts)
Charsadda |
Name of Donor/ Funding Agency
Concern WorldWide |
Duration of Project (months):
0.45 years |
Start date (month/year):
August 01, 2010 |
Completion date (month/year):
Dec 31, 2010 |
No. of Project Staff
17 persons
|
Name of senior employees of your organization involved in project implementation
|
Project Objectives, Outcomes and list of major activities (Not more than 500 words)
The following are the headline amounts of the key outputs/services delivered:
- Flood affected families have access to clean drinking water
- Flood affected families have increases awareness regarding hygiene, DRR and climate change
- Flood victims have access to necessary household accessories (asset transfer)
List of major activities (along with targets)
- Social Mobilization to mobilize COs/VOs/LSOs
- Conducting Poverty Scorecard Survey to identify poorest families
- Procurement of household kits
- Procurement of hygiene kits
- Distribution of household & hygiene Kits
- Water tankering
Awareness regarding hygiene promotion, gender, DRR and nutrition