Rapid Onset Emergency Project II

Rapid Onset Emergency Project II
Approx. value of the contract: 38 million PKR
Country

Pakistan

Location within Country (Districts)

Mardan

Name of Donor/ Funding Agency

Oxfam GM

Duration of Project (months):

0.5 years

Start date (month/year):

Aug 01, 2009

Completion date (month/year):

Dec 31, 2009

No. of Project Staff

 

34 persons

 

Name of senior employees of your organization involved in project implementation[1]

  • Syed Shah Nasir Khisro (ED)
  • Fazal Ullah (Finance Manager)
  • Saif Khan(Project Manager)
  • Imran Khan (Monitoring Officer)

Project Objectives, Outcomes and list of major activities (Not more than 500 words)

The following are the headline amounts of the key outputs/services delivered:

  • 10,000 IDPs are facilitated with non-food items
  • 10,000 IDPs are provided with clean drinking water and sanitation facilities
  • Awareness regarding population spacing, hygiene promotion, nutrition and gender

List of major activities (along with targets)

  • Social Mobilization to form WASH Committees
  • Training of WASH Committees on sanitation and hygiene
  • Identification of IDPs and host families
  • Distribution of food items (assets transfer)
  • Distribution of NFIs and Hygiene Kits (assets transfer)
  • Awareness regarding hygiene promotion, gender, DRR and nutrition